Short answer

A good-quality ADU runs about $300,000 to $360,000 built. Simpler work exists below that and larger or more complicated sites go above it. We price per project rather than per square foot, for a reason worth understanding before you compare bids.

Why we won't give you a per-square-foot number

Roughly $13,500 to $18,500 of the cost happens before anyone breaks ground, and almost none of it scales with size. The architect charges the same for a 400 square foot unit as a 700. The surveyor does too. The soils report certainly does — the ground doesn't care how big the building is.

So the effective cost per square foot rises as the unit gets smaller. A flat multiplier gets the small end badly wrong, which is exactly the size range most people ask about first.

What happens before construction starts
ItemCostWhat it's for
Architectural plans + structural engineering$10,000Full permit set including Title 24. The architect also submits to the city portal
Setback survey$2,500Establishes where the unit can legally sit
Setback certification letter$500Confirms to the inspector it was built where the survey said
Geotechnical soils report$4,500–$5,500Baseline, no geohazard. Determines the foundation design
    — with liquefaction risk$8,000–$10,000Deeper testing. Real in parts of Santa Clara County
Deep-foundation special inspection~$762Only if the soils report calls for a deep or pile foundation
Permits, impact and school feesVaries by cityPulled per job — we won't publish a number we'd have to guess

Two state rules that can move your number

Impact fees are waived under 750 square feet

Under California law, ADUs under 750 square feet are exempt from local impact fees, and JADUs under 500 square feet are as well. On some jurisdictions that is a meaningful saving, and it is a genuine reason to think carefully before designing a 780 square foot unit.

Your city must offer pre-approved plans

Since January 2025, every California city and county has to run a pre-approved ADU plan program and rule on a qualifying application within 30 days. Using one can take the $10,000 plan cost off your project and collapse the permit timeline. How AB 1332 works →

What actually swings the construction number

  • Utility runs. Sewer, water, gas and electrical from the house or the street. A unit at the back of a deep lot costs meaningfully more than one near existing service.
  • Panel capacity. If the existing panel can't carry the new load, a service upgrade is real work with a utility coordination timeline attached.
  • Access. Whether a machine can reach the build area or whether material and spoil move through a side gate by hand.
  • Soils and slope. A flat lot and a graded hillside are different foundations at different prices.
  • Detached vs garage conversion. A conversion reuses an existing shell, which usually costs less — but often needs structural and envelope upgrades to become legal living space.

How to compare two ADU bids

The gap between bids is usually soft costs one included and the other left out. The four questions to ask both builders →

Common questions

How much does an ADU cost in San Jose in 2026?
A good-quality ADU runs about $300,000 to $360,000 built. Simpler work exists below that; larger units and difficult sites go above it.
Why won't you quote a price per square foot for an ADU?
Because roughly $13,500–$18,500 of the cost is fixed regardless of unit size, so the effective rate per square foot rises as the unit gets smaller. A flat multiplier is wrong at exactly the sizes people ask about most.
Are ADUs exempt from impact fees in California?
ADUs under 750 square feet are exempt from local impact fees under state law, as are JADUs under 500 square feet.
What does an ADU soils report cost?
A baseline geotechnical report with no geohazard runs $4,500–$5,500. Sites with liquefaction risk need deeper testing, typically $8,000–$10,000.
Is a garage conversion cheaper than a detached ADU?
Usually, because the shell already exists. But converting a garage into legal living space often requires structural, insulation and envelope upgrades that surprise people.

Where to go next

Written by the team at Elusive Construction, a licensed California general contractor (B #1112902) building in Santa Clara and San Mateo counties. General information about how residential construction works — not legal advice. For your specific contract, talk to an attorney.

Have a project you want priced honestly?

Book a Project Discovery Call and we'll tell you what's realistic — scope, budget and timeline — whether or not we're the right builder for it.